Stanton Avenue / Golda Meir House Expansion
160 Stanton Avenue
Auburndale, MA 02466
Goals
Expand the existing Golda Meir House through two new additions with 68 net new rental apartments. 57 units will be permanently restricted to residents at least 62 years of age. Of the 60 units that will be permanently affordable at the income levels shown below, based on the federally defined Area Median Income (AMI), 9 units without age restrictions will be designated for individuals with disabilities who have experienced chronic homelessness.
Housing Unit Mix (Updated July 2020)
Area Median Income (AMI) | 1 Bedroom | 2 Bedrooms |
---|---|---|
Up to 30% AMI * | 18 (Previously 7) |
2 (Previously 1) |
Up to 50% AMI * |
25 (Previously 20) |
0 (Previously 2) |
Up to 60% AMI |
2 (Previously 18) |
3 (Previously 2) |
Under 100% AMI |
8 (No Change) |
2 (No Change) |
No income restrictions ** | 4 (No Change) |
4** (No Change) |
Total Units | 57 | 11 |
Total Bedrooms | 57 | 22 |
* All 45 apartments for the <30% AMI and <50% AMI tiers will have project-based vouchers, which will cover the difference between 30% of residents’ actual incomes and contracted rents. The Section 8 vouchers will serve 9 nonage restricted, 1-bedroom units for chronically homeless individuals.The 9 units for formerly homeless individuals will be distributed between these two income categories and will be included in the total 30 units with vouchers, which will fill the gap between the contracted rent and 30% of the tenant's actual income (8 units through the federal Section 8 program, 22 units through the Massachusetts Rental Voucher Program).
** Of the two-bedroom units without formal income restrictions, one will be a reduced-rent unit for one or more New England Conservatory graduate students participating in the planned resident enrichment services program. The rents for all units without formal income restrictions are proposed to be offered at below the true "market rate."
Funding
$4,494,857 |
CPA Funding (2018 and 2020) |
$255,143 |
Newton HOME Funds |
$7,972,000 |
Permanent Mortgage Loan |
$14,162,000 |
Federal and State Low Income Housing Tax Credit Equity (Confirmed) |
$5,000,000 |
DHCD, HOME, HSF,AHT,NFIT Funds (Confirmed) |
$4,000,000 |
HUD Section 202 Capital Advance (Confirmed) |
$74,600 |
Utility Rebates (Expected) |
$835,400 |
Golda Rehab Savings (Confirmed) |
$480,000 |
Charles Farnsworth Trust (Confirmed) |
$1,250,000 |
Weinberg Foundation (Confirmed) |
$1,512,000 |
Additional 2Life Philanthropy (Committed) |
$400,000 |
Deferred Developer Fee (Committed) |
$40,436,000 |
Total Project Cost |
Contact
All staff below are based at:
2Life Communities
30 Wallingford Road
Brighton, MA 02135
Lizbeth Heyer
Chief of Real Estate and Innovation
lheyer@2lifecommunities.org
617-912-8475
Zoe Weinrobe
Director of Real Estate Development
zweinrobe@2lifecommunities.org
617-912-8406
Ithzel Polanco-Cabadas
Real Estate Project Manager
ipolanco@2lifecommunities.org
617-912-8490
City of Newton Contact:
Lara Kritzer, Community Preservation Committee Manager
Funding Process
2020
July 10, 2020 - New Proposal Submitted for $1,244,857 in additional CPA funding. The Cover Letter explains the need for the additional funding and the proposal itself includes the application, updated project budget, and supporting materials including additional funding approval letters.
July 2020 -Memorandum on maximum HOME funding limits per unit
August 10, 2020 - Four Letters of Support for the additional funding received.
August 7, 2020 - Planning and Development Board Memorandum for August 11 Meeting
August 11, 2020 - Project Presentation to the CPC and Planning and Development Board
August 24, 2020 - CPC Recommendation for full project funding submitted to City Council for review and approval.
October 5, 2020 - City Council Order issued approving additional project funding as requested.
October 20, 2023 - Final Report submitted for review and approval at CPC meeting on November 14, 2023
2018-2019
- 8 June 2018 - Pre-proposal, discussed with CPC 10 July 2018
- 7 September - 8 November 2018 - Full proposal, with attachments below (see 3 December 2018 revisions below):
- Photos & maps
- Project budgets & funding sources
- Project sponsor finances & qualifications
- Evidence of site control, commitment to deed restriction
- Community outreach
- Fair housing, tenant selection plan, relocation policy, architectural access
- Unit mix and operating budget (submitted separately but now integrated into full proposal)
- 7 September - 8 October 2018 - additional proposal attachments, posted separately:
- Market analysis
- Appraisal
- Design, site & floor plans, sustainability (large-scale plans best viewed online, may not print legibly on letter- or legal-size paper)
- Online petition of support submitted by JCHE as of 12 October 2018
- 6 October 2018 - Community letters submitted to date
- 9 October-6 November 2018 - Presentation to CPC public hearing (see 3 December 2018 revisions below) and sponsor responses to public hearing questions
- Note: The revisions below submitted 3 December 2018 eliminated the wellness center previously proposed as part of this project. This center could not have used CPA funds.
- 3 December 2018 proposal revisions:
- Updated proposal summary & budgets, with elevations & floor plans
- Updated presentation (PowerPoint)
- 24 October-12 December 2018 - CPC funding recommendation
- 17 December 2018 - City Council appropriation order
- 20 September 2019 - Funding/project status update to Newton CPC (please note that documents above do not reflect this update)
Project Background & News
This project incorporates a small parcel previously owned by the City of Newton.
- August 2017 - City of Newton Request for Proposals (RFP) for Stanton Avenue parcel with surplus water tower
- October 2017 - JCHE response to City RFP
- 4 February 2020 - State funding awarded, including Low-Income Housing Tax Credits (LIHTC)