City of Newton, MA
Home MenuEddy Street
Affordable Housing
54 Eddy Street
Newtonville, MA 02465
Goals
Create 2 units of permanently affordable rental housing, one for households at up to 50% of the area median income and one for households up to 80% in a two-family house with a total of 5 bedrooms, built in 1914.
Funding
$243,572 | CPA funds (community housing) $11,428 of the original $255,500 CPA grant was returned unspent upon completion. |
$690,250 | CDBG funds |
$120,000 | Long-term bank mortgage |
$50,000 | Foundation grant |
$1,103,822 | Total Project Cost |
Contact
Jennifer Van Campen, Executive Director
Citizens for Affordable Housing Development in Newton Organization (CAN-DO)
79-B Chapel Street
Nonantum, MA 02458
jvc@metrowestcd.org
617-923-3505
Proposal Review & Appropriations
- 13 June 2012 - Pre-proposal, including preliminary budget
- 14 June 2012 - Online realtor photos (received 30 August 2012. previous versions rec'd June-July 2012, then updated; this long file may load slowly.)
- 30 August 2012 - Full proposal (revised from June & July 2012 versions), including development and operating budgets (this long file may load slowly), including:
- Home inspection report (11 June 2012)
- Appraisal for bank (23 July 2012)
- Acquisition/site control documents: deed, mortgage & assignment of rents (31 July 2012) This long document may load slowly,
- 24 August 2012 - Letter from Newton Housing Partnership to Planning & Development Board, re: request for CDBG and CPA funds
- September-October 2012 - Additional information:
- Independent appraisal commissioned by CPC 13 September 2012)
- Site photos taken by City of Newton Housing staff (18 September 2012) (This large file may load slowly.)
- Updated project scope of work & cost estimates (19 September 2012)
- Other funding sources being explored (letter from developer, 19 September 2012)
- Current financial statements for CAN-DO and its past completed projects, submitted for review by the Planning & Development Board
- Memo from City of Newton Housing staff to Newton Planning & Development Board & Community Preservation Committee (this 26 October 2012 version replaces the 2 August 2012 version addressed to the Newton Housing Partnership)
- 5 & 14 November 2012 - Presentation in support of proposal, to Newton Planning & Development Board & Community Preservation Committee
- Architect's photos, in support of development budget/scope of work (this very large file may load slowly)
- Petition (citizen signatures) supporting the project, as submitted by proposal sponsor
- 27 November 2012 - CPC funding recommendation
- 17 December 2012 - Board order (appropriation)
Project News
- 25 March 2013 - CPA funding agreement, including affordable housing covenant/ restriction as recorded at Registry of Deeds
- 20 March 2013 - Mortgage securing CDBG funds
- 15 May 2013 - Construction contract
- 17 July 2013 - Building permit
- 6 August 2013 - Affirmative marketing plan
- April-May 2014 - Final project report (including photos)