Levingston Cove is one of the four public open space parcels set along the shore of Crystal Lake, a 33 acre glacial kettle pond in Newton Highlands. The crescent shaped cove is is bordered by a grassy slope and its inaccessible shoreline pathway is now severely eroded. The current CPA funding request is for construction funds to implement a conceptual design and plan for the area which will correct erosion damage, install new features to better deal with runoff, and  construct new accessible walkways.

Funding:

$1,440,344           Newton CPA Funds

$24,255                City Staff Time to oversee and manage project

$50,000                Conceptual Plan Development (State funded grant)

$8,295                  Topographic Survey to be completed by Newton DPW

$88,000                Additional Design Development through Bidding Process                                                        (Requested from State)

$25,000                Construction Oversight (State funds)

$1,635,894          Total Project Funding 

Contacts:

Luis Perez Demorizi, Open Space Coordinator

Parks, Recreation, and Culture Department

246 Dudley Road

Newton, MA 02459

lpdemorizi@newtonma.gov

  

Nicole Banks, Commissioner 

Parks, Recreation, and Culture Department

246 Dudley Road

Newton, MA 02459

nbanks@newtonma.gov

 

Funding Process:

April 23, 2021 - Pre-Proposal submitted for discussion with CPC at their May 11, 2021 regular meeting.  Pre-Proposal materials include the following:

May 11, 2021 - Pre-Proposal Presentation reviewed by the CPC. Project is invited to submit a full proposal for consideration at a public hearing. Anticipate that the proposal will be submitted in time for the June 8 CPC meeting.

May 21, 2021 - Full Proposal submitted for review including the following materials:

 June 2, 2021 - Letter and Presentation received from Friends of Crystal Lake submitted with suggested changes to project design

June 8, 2021 - Project Presentation made during CPC's Public Hearing on the Full Proposal. CPC unanimously votes to recommend full funding of the project to the City Council for approval.

July 12, 2021 - CPC Funding Recommendation sent to City Council for their review and approval.

September 20, 2021 - New Levingston Cove Improvement Project Fact Sheet issued

October 12, 2021 - Project Update following City Council's chartering of funding vote to their October 18 meeting.

October 18, 2021 - City Council Order approves full funding of the project.